Footings Calculator — Continuous Footings by the Run
For foundation footings, stem walls, deck ledgers, and retaining-wall bases. Enter one run's length, the footing width and depth, and how many identical runs you are pouring.
Your footings
Prices — national-average defaults, edit to your local prices
Defaults are planning averages, not quotes. Your supplier's prices are the real ones — type them in.
Estimates only, for planning. Footing size and depth are code items — the bottom of the footing must sit below your local frost line, and width depends on soil and load. Confirm with your building department or engineer before you dig.
Footing basics worth knowing
- Frost line first: the footing's bottom must be below the frost depth for your area — from a few inches in the deep South to 4+ feet up north. Depth in this calculator is the footing's thickness, not the trench depth.
- Width spreads the load: a common rule is the footing extends about the wall's thickness on each side. Soft soil needs wider footings.
- Undisturbed soil: pour on soil that has not been dug up and refilled loose; if you over-dig, fill the extra with concrete (and count it in your volume) — never with loose dirt.
Frequently asked questions
How deep should a footing be?
Two different numbers: the footing itself is typically 8–12 inches thick, and its bottom must rest below the local frost line. Your trench depth is frost depth plus footing thickness. Frost lines are set by local code — look yours up before digging.
Can I use bags for footings?
For a short run or a couple of deck footings, yes. A house foundation at 5+ cubic yards is truck work — footings need to be poured continuously so they cure as one piece.
Do footings need rebar?
Most codes require continuous horizontal rebar in foundation footings (commonly two #4 bars). This calculator figures concrete volume only; rebar is figured separately by length.